hempcrete extension to Victorian terrace:

2013

timber frame and hempcrete contractor

 

I designed the frame and hempcrete details and myself and Rob constructed the foundations, plinth, Frame and cast the hempcrete walls and roof.

I later went back and cast a hempcrete floor internally also.

The walls were 2 cubic metres of hempcrete which we completed in one day with myself, Rob and the client. We used a normal cement mixer for mixing.

We did the ceiling and roof in less than a day.

This was the first ceiling I did where the battens holding the hempcrete up were completely engulfed in hempcrete and don’t show on the underside when the shuttering is removed.